Engineering and construction company, Zinfra Southern Contracting, has completed work on a Horizon Power transmission line project in WA.

Zinfra was awarded the contract for the Horizon Power X2 and X1, 220kV line construction project in June 2015.

The project consisted of 6.3 kilometres of overhead transmission line (towers and mono poles), 800 metres of underground 220kV cable, three cable termination poles, and associated civil work and related infrastructure components.

The project was located near Port Hedland in Western Australia and work was undertaken under the direction of GHD Perth.

A small bush fire and high winds delayed the project for a short time in late 2015, before crews were able to resume work in early October.

The transmission line work has now been completed and powerlines are energised.

Jessica Dickers is an experienced journalist, editor and content creator who is currently the Editor of Utility’s sister publication, Infrastructure. With a strong writing background, Jessica has experience in journalism, editing, print production, content marketing, event program creation, PR and editorial management. Her favourite part of her role as editor is collaborating with the sector to put together the best industry-leading content for the audience.

©2024 Utility Magazine. All rights reserved

CONTACT US

We're not around right now. But you can send us an email and we'll get back to you, asap.

Sending

Log in with your credentials

Forgot your details?